Professional-grade padel courts built to international standards with premium materials and expert craftsmanship.
SPECIFICATIONS
All our padel courts are built to FIP (International Padel Federation) standards, ensuring your facility meets international competition requirements.
20m × 10m (65.6ft × 32.8ft) playing area with a minimum internal height of 6m
COMPONENTS
Hot-dip galvanized steel frames provide the backbone of every court. Our structures are engineered to withstand tropical weather conditions and are rated for wind loads up to 120 km/h.
10mm or 12mm tempered safety glass panels on the back and side walls. These panels are designed to absorb ball impact while providing excellent visibility for spectators.
Welded steel mesh with 45mm × 45mm aperture sits above the glass walls. Powder-coated for durability and available in various colors to match your branding.
Reinforced concrete foundations designed for local soil conditions. We work with geotechnical engineers to ensure long-term stability in tropical climates.
Premium synthetic grass with silica sand infill creates the perfect playing surface. Proper drainage ensures playability even after heavy rain.
Professional LED floodlights providing 400-500 lux illumination. Designed to minimize glare while ensuring consistent visibility across the entire court.
TECHNICAL DATA
| COMPONENT | SPECIFICATION | STANDARD |
|---|---|---|
| Playing Area | 20m × 10m (±10mm tolerance) | FIP Certified |
| Minimum Height | 6m internal clearance | FIP Certified |
| Glass Panels | 10mm/12mm tempered safety glass | EN 12150 |
| Steel Frame | Hot-dip galvanized (min. 80μm) | ISO 1461 |
| Mesh Aperture | 45mm × 45mm (max 50mm × 50mm) | FIP Standard |
| Turf Pile Height | 12-15mm fibrillated | ITF Approved |
| Sand Infill | Silica sand, 4-6kg/m² | Manufacturer Spec |
| Lighting Level | 400-500 lux (min. 300 lux) | FIP Recommended |
COURT TYPES
Perfect for Thailand's climate with proper drainage and UV-resistant materials.
Climate-controlled facilities offering year-round playability regardless of weather.
TIMELINE
Foundation work and base preparation
2-3 weeks
Frame assembly and anchoring
1-2 weeks
Wall panel installation
1 week
Surface, lighting, and details
1-2 weeks
6-8 weeks from groundbreaking to play-ready court (single court). Multi-court facilities require additional planning.